Fables Template

Transnet Rail Infrastructure Manager

Announcements

Fables Template

Announcements of Changes to the Network Statement

This page provides a consolidated view of formal announcements issued by Transnet Rail Infrastructure Manager (TRIM) relating to changes, updates and clarifications to the Network Statement and its Annexures.

How to use this page: Use the Month & Year links on the left (or pills on mobile) to jump quickly to a specific period. Layout: Row 1 of each card shows the announcement title and date; Row 2 shows the full content.

December 2025

Announcements issued in December 2025.

Heading: TRIM announces the release of Ad-hoc Train Path Applications
01 December 2025
In line with clause 4.3.4 of the Network Statement Volume 3, Applications for once-off traffic (ad-hoc services) will be allocated capacity on an as-and-when-available basis. Applicants must adhere to the same criteria articulated in the slot application process, the major different is the duration of the application, evaluation and allocation of slots which is much shorter as the slots are usually once off. Requests for ad-hoc services shall be presented at least 21 days prior to the date of service, and the IM will provide positive or negative answer within 1 to 14 days, except for new TOCs that must follow the application process as set out in paragraph 4.3.2.

TRIM is pleased to advise that submissions for Ad-hoc Train Path Applications are now open.

This process provides rail network access outside of the annual slot allocation cycle, specifically designed to accommodate once-off, urgent, and unforeseen operational requirements. It also ensures flexibility and responsiveness to meet industry needs such as:
  • Additional train movements during ramp-up periods
  • Increased demand in peak traffic periods
  • Material trains for special projects
  • Breakdown trains for emergency recovery operations, among others

Interested parties are invited to submit applications in line with the guidelines outlined in the Network Statement Volume 3, Annexure 32.


Click here to apply

For further information, please contact us at infrastructuremanager@transnet.net

February 2025

Announcements issued in February 2025.

Extended Deadline for Network Access Applications to 27 February 2025
05 February 2025
In response to requests from potential participants, Transnet Rail Infrastructure Manager (TRIM), in consultation with key stakeholders, has approved an extension of the closing date for Network Access Applications from 07 February to 27 February 2025. The extension will provide an opportunity for applicants to review and consider the updated Annexure 29B – Network Capacity Statement and the Addendum to Section 4-10 of the Network Statement. Please refer General Enquires to infrastructuremanager@transnet.net and Network Access application to slotapplications2024_q4@transnet.net

MEDIA STATEMENT: Click to download PDF

January 2025

Announcements issued in January 2025.

Please be advised that TRIM has amended its banking account details in Annexure 29a Network Access Application Form.
24 January 2025
The updated Annexure 29a is now available for download on our website. Train Operating Companies (TOCs) are requested to use the updated banking details for all payments to avoid processing delays. Should you require further assistance, please contact us at infrastructuremanager@transnet.net
Changes to Annexure 29b Network Capacity Statement
24 January 2025
The train length (number of wagons) for the OD pair Pendoring to RCB has been changes from 50 to 75 wagons.
Region Corridor Origin Destination Train Length (# of wagon) Typical Cargo Nett Tons/wagon Frequency (# of trains/week) Total Annual Capacity (Mil Tons) Designed Travel Times (Hh:Mm) Actual Travel Times (Hh:Mm) Train Type (Air/Vacuum brake)
Eastern Region North Pendoring Richards Bay 75 Chrome 58 1 train/week 0,139 28:24 36:56 Air Brake

April 2024

Announcements issued in April 2024.

IRERC has extended the date for submission of written responses to the draft Network statement as published in the Government Gazette No. 50312
17 April 2024
to the 20 May 2024 before 11h00am Interested parties who wish to submit written comments should address them to Irercsec@dot.gov.za or visit the Department of Transport website, https://www.transport.gov.za under the IRERC link.

March 2024

Announcements issued in March 2024.

Interested parties are advised to take note that the published Rail Access Tariff Methodology document
26 March 2024
submitted to IRERC in November 2023, indicates that "IM will begin offering open access from 1 April 2024", however, the date for opening of applications is subject to the conclusion of the public consultation process facilitated by IRERC and finalization of tariffs.
Annexure 29 has been updated
26 March 2024
Annexure 29 has been updated to "Slot Application Request Template" with revisions and condensing of the application document content.
Annexure 27 b & c Consolidation
26 March 2024
Annexure 27 b & c has been consolidated into 1 document.
Annexure 2-12 has been removed
26 March 2024
Annexure 2-12 has been removed and will be made available when applications are lodged.
Annexure 1 has been updated
26 March 2024
Annexure 1 has been updated with the latest shut down schedule for 2024/25.