The purpose of the Ad-hoc capacity process is to grant rail network access outside of the annual or quarterly slot allocation cycles. It is designed to meet urgent, unforeseen, or once-off operational requirements such as extra train movements (Ramp up, peak period, material and breakdown trains).
TOCs must submit request for ad-hoc allocation at least 72 hours and up to 21 days before planned train movement.
Ad-Hoc Train path Application Form
Rolling Stock Roadworthy Certificate
Crew qualification and availability
Signed Rail Access Agreement
Signed Interface Agreement
Valid RSR Safety Permit
Compliance Certificate/s (where applicable) e.g Hazardous Goods